Check out new traffic scheme as Skyway Extension work regains ground

May 26, 2020

THE construction of the P10-billion Skyway Extension project is moving at a steady pace following the go-signal given by the government to resume work almost two weeks ago.

As part of San Miguel Corporation’s effort to get back on track with the construction of the project following a 60-day delay due to the enhanced community quarantine, the Skyway Alabang Toll Plaza Southbound Entry will be closed from May 31 to June 15.

A new traffic scheme will be implemented with the help of the Muntinlupa Traffic Management Bureau (MTMB) due to the temporary closure.

Private cars are advised to take Filinvest Entry and/or National Road to Susana Heights Entry, while trucks and buses are instructed to take National Road to Susana Heights Entry.

“We are happy to report that despite the long delay due to the ECQ and the limited workforce deployed, we’ve been gaining a lot of ground in terms of construction these past two weeks. Workers are also back at the site and earning income for their families. We’re asking for the public’s continued cooperation and kind understanding for any delays our work might cause,” said SMC President and COO Ramon S. Ang.

Continue reading below ↓

Continue reading below ↓
Recommended Videos

Skyway’s contractor, EEI Corporation, has strictly enforced safety, sanitation and other health measures at the work site. These include: following the basic rules of social distancing, the use of face masks and gloves, and providing hand sanitation and disinfecting facilities, on top of on-site housing, for workers.

“These health and safety measures will remain in place while we work on delivering this critical project to the public,” Ang added.

Continue reading below ↓

The project’s original target completion date was December 2020, but the two-month delay due to the pandemic is likely to push this back a little.

San Miguel Infrastructure, SMC’s concession holder for the Metro Manila Skyway, said that the closure of the Skyway Alabang Toll Plaza Southbound Entry will make way for bored piling works at the southbound section, starting 6 am on May 31 until June 15.

At the resumption of the construction, Skyway management also closed about 700 meters of Lane 3 of the Skyway At-Grade section northbound from the old Alabang Entry Plaza. The one-month closure enabled workers to install scaffoldings to build the columns for Pier 34- 49.

The P10 billion project will extend Skyway from Susana Heights in SLEX to Sucat and back and will provide a direct access to the elevated section of the Skyway. With the direct access to the elevated section of the Skyway, the project is expected to ease traffic to and from the south.

Continue reading below ↓

MORE FROM SPIN
MORE FROM SPIN

    The project will also increase the number of lanes on both directions to five northbound and four southbound.